Project Timeline
|
2001
2002
-
Ad Hoc Study
Committee and music director, Tom Trenney, report progress of
initial investigations to Session
-
Research
sub-committees formed:
Organ selection
Chancel design
Finance
2003
-
Following
sub-committee reviews, Session approves selection of Nichols &
Simpson as organ builders
-
Liturgical
space design planning begins with nationally known consultant, Terry
Eason
-
Noted
acoustician, Scott Riedel, is retained to ensure acoustical quality
for music and spoken word
2004
-
Session
approves development of Capital campaign
-
Organ
construction contract approved by Session ($920,000)
-
Preliminary
design studies for sanctuary renovation begin
2005
-
Organ design
begins (3 years duration)
-
Capital
campaign raises $1.5 million
-
Congregation
feedback regarding preliminary concepts for sanctuary renovation
compiled
-
Local
architect firm (Constantine George Pappas AIA Architecture/Planning)
retained to develop final design recommendations
-
Steering
Committee named to provide project leadership and oversight
2006
-
Organ
construction begins
-
Final
sanctuary renovation design completed
-
Session
approval of design, construction, and financial plans requested
-
Construction
bids
-
Capital
campaign continues with final design plans available
2007
-
Organ
construction continues
-
Sanctuary
closes for renovation (April-December)
-
Completion:
Christmas 2007
|
|